Question

1 Approved Answer

The total cost of a project consists of fixed cost and variable cost. Fixed cost of this project is $3200 while, the variable cost of

The total cost of a project consists of fixed cost and variable cost. Fixed cost of this project is $3200 while, the variable cost of project could be estimated based upon numberof worker and duration of the project.

Each worker's salary is $4500 (for project completion) and weekly cost of the project is $15,000. The number of required workers for this project is probabilistic with the following PMF:

image text in transcribedimage text in transcribed
W 4 5 6 (Number of required Workers) 7 P(W=W) 0.25 0.15 0.20 0.40\f

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

How To Prove It A Structured Approach

Authors: Daniel J Velleman

2nd Edition

0511159439, 9780511159435

More Books

Students also viewed these Mathematics questions

Question

5. Describe how contexts affect listening

Answered: 1 week ago