The university IT team is working on the implementation of a new software system for enrollment. Using the following table, complete the requested tasks: Time

The university IT team is working on the implementation of a new software system for enrollment. Using the following table, complete the requested tasks:
Time in days Costs
Activity Immediate Predecessor Normal Crash Normal Crash
A - 6 5 $900 $1,000
B A 8 6 $300 $400
C A 4 3 $500 $600
D B 5 3 $900 $1,200
E C, D 8 5 $1,000 $1,600
a. Draw the network diagram noting normal and crash times.

B. What is the critical path?

C. What is the minimum cost of crashing the project by 4 days? Would you recommend the team crash the project? Explain your calculations and position.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Restaurant From Concept to Operation

Authors: John R Walker

6th Edition

9781118139950, 470626437, 111813995X, 978-0470626436

More Books

Students also viewed these General Management questions

Question

What are the hidden negative consequences of benevolent sexism?

Answered: 1 week ago

Question

What is the difference between hostile and benevolent sexism?

Answered: 1 week ago