The Vienna Company, which manufactures violins, has established the following standard cost per violin: Direct material 3 pounds standard price 4.00 per pound cost 12.00
The Vienna Company, which manufactures violins, has established the following standard cost per violin: Direct material 3 pounds standard price 4.00 per pound cost 12.00 direct labor 2 hours standard price 8.00 per hour 16.00 standard cost Variable mfg overhead 2 hours standard price is 5.00 per hour and standard cost is 10.00.
Vienna produced 600 violins. To produce the violins, the company used 2,000 pounds of direct materials at a total cost of $7,600; employees worked 1,100 direct labor hours and the total amount paid for direct labor was $9,240; and actual variable manufacturing overhead spending was $5,720. Variable manufacturing overhead is based upon direct labor hours.
What is the material price variance?
What is the materials quantity variance?
What is the labor rate variance?
What is the labor efficiency variance?
What is the labor spending variance?
What is the variable overhead rate variance?
What is the variable overhead efficiency variance?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started