Question
There are three finished products: Original Unscented (UO), Original Lemon Scent (OS), and Extra-Strength Unscented (EU). Production stages: a. Mixing - 1 mixer (M1) b.
There are three finished products: Original Unscented (UO), Original Lemon Scent (OS), and Extra-Strength Unscented (EU).
Production stages:
a. Mixing - 1 mixer (M1)
b. Scent/additives - 2 stations for scents/additives (S1, S2)
c. Packaging - 2 Packaging lines (P1, P2)
Develop a scheduling challenge that involves the 3 finished products from above that have at least 3 customer orders with ship dates and times that align with commit dates already relayed to customers. Additionally, assume there are 7 machines involved in the schedule. b. Create data tables needed to build a production schedule including: i. Open Customer Orders ii. Production Rates iii. Production Yields iv. Build of material v. Production Sequence/Transition Matrix vi. Changeover and Setup Times vii. Others? c. Define Basic Rules to Create Initial Schedules (Rule Based) d. Create/Define Genetic Algorithm to Develop/Improve Schedules
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started