There is an 81 percent chance the project below can be completed inXweeks or less ACTIVITY MOST OPTIMISTIC MOST LIKELY MOST PESSIMISTIC A 5 5
There is an 81 percent chance the project below can be completed inXweeks or less
|
ACTIVITY | MOST OPTIMISTIC | MOST LIKELY | MOST PESSIMISTIC | |
A | 5 | 5 | 11 | |
B | 3 | 3 | 3 | |
C | 2 | 3 | 13 | |
D | 4 | 7 | 10 | |
E | 5 | 6 | 13 | |
|
What is X?