Question
Time Proj A Proj B 0 (1,000,000) (500,000) 1 100,000 300,000 2 300,000 150,000 3 400,000 100,000 4 500,000 50,000 a) Calculate the IRR for
Time | Proj A | Proj B |
0 | (1,000,000) | (500,000) |
1 | 100,000 | 300,000 |
2 | 300,000 | 150,000 |
3 | 400,000 | 100,000 |
4 | 500,000 | 50,000 |
a) Calculate the IRR for each project and the incremental IRR (if it exists). Round your answers to 2 decimal places.
b) Calculate the NPV for each project using a discount rate of 8%
c) If these projects are mutually exclusive, and a discount rate of 8% is used, identify which project(s) you would accept? Clearly explain the logic behind your decision.
d) If these projects are independent, and a discount rate of 8% is used, identify which project(s) you would accept? Clearly explain the logic behind your decision.
e) You do not need to construct an NPV profile graph for this answer, but use the project IRRs and incremental IRR (if it exists) to explain how the choice of projects is sensitive to the discount rate used. Clearly explain all of the conclusions that can be drawn from the information
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started