To estimate a project's future performance, a project manager must study the project's progress data over numerous reporting periods for repetitive patterns in performance. What
To estimate a project's future performance, a project manager must study the project's progress data over numerous reporting periods for repetitive patterns in performance. What is this analysis known as? Question 25 options: Variance analysis Performance analysis Monitoring analysis Trend analysis