Tomorrow Company has the following information available: Budgeted cost of direct materials at 900,000 untes $900,000 Budgeted cost of direct materials at 820,000 units $820,000
Tomorrow Company has the following information available:
Budgeted cost of direct materials at 900,000 untes $900,000
Budgeted cost of direct materials at 820,000 units $820,000
Actual cost of direct materials at 820,000 unites $840,000
Actual level of output (units) 820,000
Planned level of output (units) 900,000
The cost driver of product costs is units of ouput. What is the static budget variance for direct material costs?
A) $60,000 Favorable B) $60,000 Unfavorable C) $20,000 Unfavorable D) $20,000 Favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started