Twelve (12) machines are planned to be used for a 60-day production run for a major customer. The actual operating time is 1440 hours. Upon
Twelve (12) machines are planned to be used for a 60-day production run for a major customer. The actual operating time is 1440 hours.
Upon failure, a machine must be returned to the manufacturer for repair. The turnaround time is at least 90 days and an average of 110 days.
The per machine failure rate is 0.01 failures per operating hour
(a) What is the expected number of machine failures during the production run?
(b) Determine the number of spare machines required so that the probability of exceeding this number is 5%.
(c) What is the probability that the number of spare machines required will exceed the expected number?
(d) What is the probability of no machine failure during 8 operating hours (a shift)?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started