Two-Stage ABC for Manufacturing Detroit Foundry, a large manufacturer of heavy equipment components, has determined the follow- ing activity cost pools and cost driver levels
Two-Stage ABC for Manufacturing
Detroit Foundry, a large manufacturer of heavy equipment components, has determined the follow-
ing activity cost pools and cost driver levels for the year:
Activity Cost Pool Activity Cost Activity Cost Driver
Machine setup. . . . . . . . . . . . . . . . . . . $660,000 12,000 setup hours
Material handling. . . . . . . . . . . . . . . . . 100,000 2,000 tons of materials
Machine operation . . . . . . . . . . . . . . . 450,000 10,000 machine hours
The following data are for the production of single batches of two products, C23 Cams and U2
Shafts during the month of August:
C23 Cams U2 Shafts
Units produced ........................................................500 300
Machine hours...........................................................4 5
Direct labor hours ..................................................200 400
Direct labor cost .................................................$5,000 $10,000
Direct materials cost...........................................$30,000 $20,000
Tons of materials...................................................12.5 8
Setup hours..............................................................3 7
Required
Determine the unit costs of C23 Cams and U2 Shafts using ABC.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started