Use the data below for problems 6 to 10. Year Proj Y Proj Z 0 ($210,000) ($210,000) 1 200,000 95,000 2 95,000 78,000 3 73,000

Use the data below for problems 6 to 10.

Year

Proj Y

Proj Z

0

($210,000)

($210,000)

1

200,000

95,000

2

95,000

78,000

3

73,000

4

87,500

The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have an 11% cost of capital.

6. What is each projects initial NPV without replication?

7. What is each projects equivalent annual annuity?

8. Now apply the replacement chain approach to determine the shorter projects extended NPV. Which project should be chosen?

9. Now assume that the cost to replicate Project Y in 2 years will increase to $140,000 because of inflationary pressures. How should the analysis be handled now, and which project should be chosen?

10. You are also considering another project which has a physical life of 3 years; that is, the machinery will be totally worn out after 3 years. However, if the project were terminated prior to the end of 3 years, the machinery would have a positive salvage value. Here are the projects estimated cash flows:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Supply Chain Finance And Blockchain Technology The Case Of Reverse Securitisation

Authors: Erik Hofman, Urs Magnus Strewe, Nicola Bosia

1st Edition

3319623702, 978-3319623702

More Books

Students also viewed these Finance questions