Question
Use the data below for problems BELOW Year Proj Y Proj Z 0 ($210,000) ($210,000) 1 200,000 95,000 2 95,000 78,000 3 98,000 73,000 4
Use the data below for problems BELOW
Year | Proj Y | Proj Z |
0 | ($210,000) | ($210,000) |
1 | 200,000 | 95,000 |
2 | 95,000 | 78,000 |
3 | 98,000 | 73,000 |
4 | 87,500 | |
5 | 75,000 | |
6 | 75,000 |
The projects provide a necessary service, so whichever one is selected is expected to be repeated into the foreseeable future. Both projects have an 11% cost of capital.
A. What is each projects initial NPV without replication?
B. What is each projects equivalent annual annuity?
C. Now apply the replacement chain approach to determine the shorter projects extended NPV. Which project should be chosen?
D. Now assume that the cost to replicate Project Y in 2 years will increase to $275,000 because of inflationary pressures. How should the analysis be handled now, and which project should be chosen?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started