Question
Use the following information to answer Questions 34-37. Use space below for the network. The table shown, below, reports a project's activity times (in days)
Use the following information to answer Questions 34-37. Use space below for the network.
The table shown, below, reports a project's activity times (in days) and precedence relationships.
activity | Time (days) | Predecessors |
A | 5 | NONE |
B | 8 | NONE |
C | 15 | A, B |
D | 12 | A, B |
E | 26 | C, D |
F | 33 | C, D |
G | 8 | B, F |
H | 6 | E, F |
I | 28 | G |
J | 15 | G, H |
K | 13 | G, H |
34. What is your estimate of completion time for this project?
a. 53 days
b. 92 days
c. 169 days
d. 110 days
35. What is the Earliest Start (ES) time for activity F?
a. 18
b. 23
c. 53
d. 61
36. What is the Critical path?
a. B, C, F, G, I
b. B, D, G, I
c. B, D, E, G, I
d. All activities are critical and must be complete on time
37. What is the slack for activity B?
a. 9 days
b. 14 days
c. 20 days
d. 0 days
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started