Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Use the following Table to answer the questions. Activity Predecessor Duration (weeks) A - 8 B - 8 C A 6 D A 6 E

Use the following Table to answer the questions.

ActivityPredecessorDuration (weeks)
A-8
B-8
CA6
DA6
EB4
FD, E3
GC4
HF, G6

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed
28 2 points What is the project duration? 18 24 O 23 O 25 29 2 points What is the critical path for this schedule? O ACGH ABDFH O BEFH ADFH 30 3 points What is the Early Start, Early Finish for Activity E? O 9, 15 11, 15 8, 12 O 8, 143 points What is the Late Start, Late Finish for Activity F? 14, 18 8,12 11, 15 15, 18 2 points What is the Total Float for Activity B? O 3 1 2 2 points What is the Free Float for Activity F? 2 3 O 1 34 3 points What is the Expected duration for this PERT schedule? O 24.33 23.13 O 25.17 O 26 35 2 points What is the expected duration for Activity B 2 O 5.17 O 1 O 3 36 2 points What is the critical path of this PERT schedule? O CFEH O CEG O ABD O CFH3 points What is the Early Start, Early Finish for Activity D? 12.5, 16.67 14, 18.33 10, 15.50 9, 17 3 points What is the variance for Activity (3? 0.44 .11 2.25 1.00 3 points What is the Late Start, Late Finish for Activity F? 13, 17 9, 17 14, 18.33 9, 14 4 points What is the probability that the project can be completed in 26 days? 100% 14.2% 85.8% 84.10% 3 points What is the probability that the project can be completed in 22 days? 6.80% 84.10% 50.0% 11.80% 3 points What is the total variance for the critical path? 6.00 2.44 3.36 1.00 2 points 5 What is the duration of the project under normal conditions? Type your answer... 2 points 5 What is the total normal project cost for completing the project under normal conditions? Type your answer... 3 points 5 What activities are on the critical path? BDCG BDEF ACG BEF 2 points What is the cost unit for Activity E? Type your answer... 2 points What is the cost unit for Activity E? Type your answer... 2 points What is the crash unit cost for Activity D? 500 4500 625 O 3 points The owner wants to shorten the total duration by 2 weeks. Which activity should be shortened? F B O c E 3 points What will be the crash cost for this shortening by two weeks this activity? Type your answer... 3 points What will be the crash cost for this shortening by two weeks this activity? Type your answer... 3 points What is the total crash cost if we were to crash the whole schedule without doing any easing of activities? Type your

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Operations Across The Supply Chain

Authors: Morgan Swink, Steven Melnyk, Janet L. Hartley, M. Bixby Cooper

4th Edition

1260547639, 978-1260547634

More Books

Students also viewed these General Management questions

Question

=+interactive online components, out-of-home messages, print ads,

Answered: 1 week ago

Question

=+Why does the brand want to advertise?

Answered: 1 week ago

Question

=+12. Did your concept illustrate the brand's personality?

Answered: 1 week ago