Question

1 Approved Answer

Use the longest work element rule to balance the assembly line described in the following table and figure below so that it will produce 50

 

Use the longest work element rule to balance the assembly line described in the following table and figure below so that it will produce 50 units per hour.

a. What is the cycle time?

b. What is the theoretical minimum number of workstations?

c. Which work elements are assigned to each workstation?

d. What are the resulting efficiency and balance delay percentages?

e. Use the shortest work element rule to balance the assembly line. Do you note any changes in the solution?

A 32 65 80. 20 08 20 F 12 E D 16 45 & 35 60 H 10 K 10 Work Element ABCDEFGHI C K Total Time (sec) Immediate Predecessor(s) 32 20 65 16 45 12 20 10 60 35 10 325 None AABCC D, E F G J, H, I

Step by Step Solution

3.41 Rating (154 Votes )

There are 3 Steps involved in it

Step: 1

Solution a Cycle time Demand 50 units per hour Time foe one unit 6050 min or 606050 sec 72 sec Cycle ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra

10th edition

978-013280747, 132807394, 9780132951814, 132807475, 132951819, 978-0132807395

More Books

Students also viewed these General Management questions

Question

Does log 81 (2401) = log 3 (7)? Verify the claim algebraically.

Answered: 1 week ago