Question

1 Approved Answer

Use the Nightingale Gantt Chart Template for the three images below please use the following to answer only what the images ask. Construct a project

Use the Nightingale Gantt Chart Template for the three images below please use the following to answer only what the images ask.

Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish.

Develop the Gantt chart schedule for the project to determine its estimated completion date. (Note: the template provided already has weekends and holidays removed and will start on January 3, 2017.)

Prepare a memo that answers the following questions:

Will the project as planned meet the October 25, 2017 deadline?

What activities lie on the critical path?

How sensitive is this network?

Read and complete the Nightingale Project case below.

NIGHTINGALE PROJECT

You are the assistant project manager to Rassy Brown, who is in charge of the Nightingale project. Nightingale was the code name given to the development of a handheld electronic medical reference guide. Nightingale would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations.

Rassy and her project team were developing a project plan aimed at producing 30 working models in time for MedCON, the biggest medical equipment trade show each year. Meeting the MedCON October 25, 2017 deadline was critical to success. All the major medical equipment manufacturers demonstrated and took orders for new products at MedCON. Rassy had also heard rumors that competitors were considering developing a similar product, and she knew that being first to market would have a significant sales advantage. Besides, top management made funding contingent upon developing a workable plan for meeting the MedCON deadline.

The project team spent the morning working on the schedule for Nightingale. They started with the WBS and developed the information for a network, adding activities when needed. Then the team added the time estimates they had collected for each activity. Following is the preliminary information for activities with duration time and predecessors.

Nightingale Project Activities
Activity Description Duration Predecessor
1 Architectural decisions 10 None
2 Internal specifications 20 1
3 External specifications 18 1
4 Feature specifications 15 1
5 Voice recognition 15 2, 3
6 Case 4 2, 3
7 Screen 2 2, 3
8 Speaker output jacks 2 2, 3
9 Tape mechanism 2 2, 3
10 Database 40 4
11 Microphone/soundcard 5 4
12 Pager 4 4
13 Barcode reader 3 4
14 Alarm clock 4 4
15 Computer I/O 5 4
16 Review design 10 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15
17 Price components 5 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15
18 Integration 15 16, 17
19 Document design 35 16
20 Procure prototype components 20 18
21 Assemble prototypes 10 20
22 Lab test prototypes 20 21
23 Field test prototypes 20 19, 22
24 Adjust design 20 23
25 Order stock parts 15 24
26 Order custom parts 2 24
27 Assemble first production unit 10 25 - Finish to start delay of 8 non-worked business days, 26
28 Test unit 10 27
29 Produce 30 units 15 28
30 Train sales representatives 10 29

Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish. NOTE: Copy-paste and fill in the 3x3 cell set to create building blocks for your project network diagram. image text in transcribed image text in transcribed image text in transcribed

Original Project Network Diagram Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest A B c D G PMT472L 3.2 CASE STUDY: NIGHTINGALE PROUECT - PART A Will the project as planned meet the October 25, 2017 deadline? (Enter response) What activities lie on the critical path? (Enter response) How sensitive is this network? (Enter response)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J Stevenson

12th edition

2900078024107, 78024102, 978-0078024108

More Books

Students also viewed these General Management questions