Question
Use the Nightingale Gantt Chart Template for the three images below please use the following to answer only what the images ask. Construct a project
Use the Nightingale Gantt Chart Template for the three images below please use the following to answer only what the images ask.
Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish.
Develop the Gantt chart schedule for the project to determine its estimated completion date. (Note: the template provided already has weekends and holidays removed and will start on January 3, 2017.)
Prepare a memo that answers the following questions:
Will the project as planned meet the October 25, 2017 deadline?
What activities lie on the critical path?
How sensitive is this network?
Read and complete the Nightingale Project case below.
NIGHTINGALE PROJECT
You are the assistant project manager to Rassy Brown, who is in charge of the Nightingale project. Nightingale was the code name given to the development of a handheld electronic medical reference guide. Nightingale would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations.
Rassy and her project team were developing a project plan aimed at producing 30 working models in time for MedCON, the biggest medical equipment trade show each year. Meeting the MedCON October 25, 2017 deadline was critical to success. All the major medical equipment manufacturers demonstrated and took orders for new products at MedCON. Rassy had also heard rumors that competitors were considering developing a similar product, and she knew that being first to market would have a significant sales advantage. Besides, top management made funding contingent upon developing a workable plan for meeting the MedCON deadline.
The project team spent the morning working on the schedule for Nightingale. They started with the WBS and developed the information for a network, adding activities when needed. Then the team added the time estimates they had collected for each activity. Following is the preliminary information for activities with duration time and predecessors.
Activity | Description | Duration | Predecessor |
---|---|---|---|
1 | Architectural decisions | 10 | None |
2 | Internal specifications | 20 | 1 |
3 | External specifications | 18 | 1 |
4 | Feature specifications | 15 | 1 |
5 | Voice recognition | 15 | 2, 3 |
6 | Case | 4 | 2, 3 |
7 | Screen | 2 | 2, 3 |
8 | Speaker output jacks | 2 | 2, 3 |
9 | Tape mechanism | 2 | 2, 3 |
10 | Database | 40 | 4 |
11 | Microphone/soundcard | 5 | 4 |
12 | Pager | 4 | 4 |
13 | Barcode reader | 3 | 4 |
14 | Alarm clock | 4 | 4 |
15 | Computer I/O | 5 | 4 |
16 | Review design | 10 | 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15 |
17 | Price components | 5 | 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15 |
18 | Integration | 15 | 16, 17 |
19 | Document design | 35 | 16 |
20 | Procure prototype components | 20 | 18 |
21 | Assemble prototypes | 10 | 20 |
22 | Lab test prototypes | 20 | 21 |
23 | Field test prototypes | 20 | 19, 22 |
24 | Adjust design | 20 | 23 |
25 | Order stock parts | 15 | 24 |
26 | Order custom parts | 2 | 24 |
27 | Assemble first production unit | 10 | 25 - Finish to start delay of 8 non-worked business days, 26 |
28 | Test unit | 10 | 27 |
29 | Produce 30 units | 15 | 28 |
30 | Train sales representatives | 10 | 29 |
Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish. NOTE: Copy-paste and fill in the 3x3 cell set to create building blocks for your project network diagram.
Original Project Network Diagram Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest A B c D G PMT472L 3.2 CASE STUDY: NIGHTINGALE PROUECT - PART A Will the project as planned meet the October 25, 2017 deadline? (Enter response) What activities lie on the critical path? (Enter response) How sensitive is this network? (Enter response)Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started