Use the process model in Question 2 and the information below to calculate the total cost of the process. Activities A and B are performed
Use the process model in Question 2 and the information below to calculate the total cost of the process.
- Activities A and B are performed by staff with an hourly pay of $30
- Activity C is performed by staff with an hourly pay of $40
- Activities D, E performed by staff with an hourly pay of $60
- Activity F is performed by staff with an hourly pay of $40
- Activity G is performed by staff with an hourly pay of $50