Using the following project information Activity Optimistic Time Estimate(weeks) Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Immediate Predecessor(s) A 2 3 5 none
Using the following project information
Activity | Optimistic Time Estimate(weeks) | Most Likely Time Estimates (weeks) | Pessimistic Time Estimates (weeks) | Immediate Predecessor(s) | ||||
---|---|---|---|---|---|---|---|---|
A | 2 | 3 | 5 | none | ||||
B | 2.3 | 4 | 5 | A | ||||
C | 5 | 7 | 8 | A | ||||
D | 3 | 5 | 7 | B, C | ||||
E | 4 | 7 | 14 | B, C | ||||
F | 2 | 5 | 8 | D | ||||
G | 4 | 5 | 6 | E | ||||
H | 6 | 6 | 8 | F | ||||
I | 4 | 8 | 12 | G | ||||
J | 2 | 3 | 3 | H, I |
The critical path is A-C-E-G-I-J.
Activity | A | B | C | D | E | F | G | H | I | J |
---|---|---|---|---|---|---|---|---|---|---|
Variance | 0.25 | 0.20 | 0.25 | 0.44 | 2.78 | 1.00 | 0.11 | 0.11 | 1.78 | 0.03 |
(a) Calculate the probability that the project will be completed in 32 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)
P(project 32) = enter a probability
(b) Calculate the probability that the project will be completed in 36 weeks. (Round your answer to 4 decimal places, e.g. 1.7945.)
P(project 36) = enter a probability
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started