Question

1 Approved Answer

Using the normal distribution of each activity, how long does it take to complete this project? What is the confidence interval that this project will

image text in transcribed
  1. Using the normal distribution of each activity, how long does it take to complete this project?
  2. What is the confidence interval that this project will be completed in 22 days?

Would you be able to explain how to do this in Excel?

\begin{tabular}{|c|c|c|} \hline Activity Label & Predecessor Activity(s) & Time in days () \\ \hline A & - & 4(1) \\ \hline B & A & 3(0.5) \\ \hline C & A & 5(1.5) \\ \hline D & B & 6(1) \\ \hline E & C & 4(0.7) \\ \hline F & D, E & 2(0.3) \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Essential Nonprofit Fundraising Handbook

Authors: Michael A. Sand, Linda Lysakowski

1st Edition

1601630727, 978-1601630728

More Books

Students also viewed these Finance questions

Question

1. Traditional and modern methods of preserving food Articles ?

Answered: 1 week ago

Question

What is sociology and its nature ?

Answered: 1 week ago

Question

What is liquidation ?

Answered: 1 week ago

Question

Explain the different types of Mergers.

Answered: 1 week ago