Question

1 Approved Answer

Using the priority list T 2 , T 1 0 , T 4 , T 5 , T 8 , T 7 , T 9

Using the priority list T2,T10,T4,T5,T8,T7,T9,T6,T3,T1, schedule the project below with two processors.
Task 5 is done by starting at time
Task 7 is done by Processor 1, starting at time