Utilizing a decision tree, the expected NPV used to make the decision to commence the testing for a project is dependent on: all the project's
Utilizing a decision tree, the expected NPV used to make the decision to commence the testing for a project is dependent on: all the project's cash flows and probabilities over the project's entire life. the path with the highest probability of occurrence. only the cash flows related to the actual test. only the cash flows and probabilities of the most successful path