Question
WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000
WBS Element | Planned Value (PV) | Earned Value (EV) | Actual Cost (AC) |
2.01 Airframe | 48000 | 48000 | 50000 |
2.02 Engines | 22000 | 21000 | 23000 |
2.03 Avionics | 80000 | 60000 | 45000 |
2.04 Communications | 30000 | 30000 | 30000 |
2.05 Tech. Manuals | 42000 | 42000 | 48000 |
2.06 Spares | 40000 | 35000 | 42000 |
2.07 Training | 80000 | 80000 | 86000 |
Project Total | 342000 | 316000 | 324000 |
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX)
Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX?
a. | The project is $26,000 under budget. | |
b. | The project is $18,000 over budget. | |
c. | The project is $8,000 over budget. | |
d. | The project is on budget. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started