Question

1 Approved Answer

WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000

WBS Element

Planned Value (PV)

Earned Value (EV)

Actual Cost (AC)

2.01 Airframe

48000

48000

50000

2.02 Engines

22000

21000

23000

2.03 Avionics

80000

60000

45000

2.04 Communications

30000

30000

30000

2.05 Tech. Manuals

42000

42000

48000

2.06 Spares

40000

35000

42000

2.07 Training

80000

80000

86000

Project Total

342000

316000

324000

Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX)

Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX?

a.

The project is $26,000 under budget.

b.

The project is $18,000 over budget.

c.

The project is $8,000 over budget.

d.

The project is on budget.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Your Financial Future How To Take Control Of Your Financial Future

Authors: Deloris Lutke

1st Edition

979-8388730831

More Books

Students also viewed these Finance questions

Question

How many new employees were added to the Employee_Listing file?

Answered: 1 week ago

Question

What is the link to your shared folder?

Answered: 1 week ago