Answered step by step
Verified Expert Solution
Question
1 Approved Answer
We have a project ( Raise _ L ) , with these activities in days: Activity A with duration 6 and no precedents. Activity B
We have a project RaiseL with these activities in days: Activity A with duration and no precedents. Activity B with duration and predecessor. A Activity C with duration and predecessor. A Activity D with duration and predecessor B Activity E has duration and predecessors B and C Activity F has duration and predecessor D and Activity G has duration and predecessors of E and F Draw this to answer the following questions. How long is this project scheduled to take?
days
days
days
days
points
QUESTION
From question # what is the ES for Node E
points
QUESTION
From question # what is the EF for Node E
points
QUESTION
From question # what is the LS for Node C
points
QUESTION
From question # what is the EF for Node D
points
QUESTION
From question # what is the slack in node D
days
days
days
days
points
QUESTION
What is the critical path from #
A~B~D~F~G
A~C~E~G
A~B~E~F~G
A~B~E~G
points
QUESTION
From question # what is the LF for Node E
points
QUESTION
From question # what is the ES for Node C
points
QUESTION
From question # what is the slack in node E
days
days
days
days
points
QUESTION
From question # what is the LF for Node D
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started