What is 5? Complete the following MPS Record and answer questions 8, 9 and 10. Lot Size Lead Time 80 1 Quantity on Hand 45
What is 5?
Complete the following MPS Record and answer questions 8, 9 and 10. Lot Size Lead Time 80 1 Quantity on Hand 45 1 7 6 2 5 Forecast 30 30 30 30 35 35 35 35 lolalo Customer Orders (Booked) 20 35 15 40 Projected On-Hand Inventory MPS Quantity MPS start Available-to-Promise Inv (ATP) 4) What is the MPS Start for Week1 of the completed plan above? A) 0 B) 30 C) 45 80 5) What is the ATP Start for Week 4 of the completed plan above? A) 0 B) 25 C) 65 D) 80Step by Step Solution