What is the buyer's risk when the probability of outsourced function being disrupted is 2% and the cost of a disruption is $4,000,000 ? Select
What is the buyer's risk when the probability of outsourced function being disrupted is 2% and the cost of a disruption is $4,000,000 ? Select one: a. $100,000 b. $250,000 c. $80,000 d. $500,500