Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

What is the expected duration for Activity B What is the Expected duration for this PERT schedule?' What is the critical path of this PERT

What is the expected duration for Activity B

What is the Expected duration for this PERT schedule?'

What is the critical path of this PERT schedule?

What is the Early Start, Early Finish for Activity D?

What is the variance for Activity G?

What is the Late Start, Late Finish for Activity F?
What is the probability that the project can be completed in 26 days?
What is the probability that the project can be completed in 22 days?
What is the total variance for the critical path?

Use the following table of activities and their respective optimistic, most likely, and pessimistic activity durations the these questions. Be sure to carry two decimal places for activity durations.

Activity Predecessor optimistic most likely pessimistic
A - 6 8 10
B A 1 2 3
C - 6 9 12
D B 2 5 11
E C 5 8 11
F C 2 4 8
G D,E 6 7 10
H E,F 4 6 8

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Fundamentals Of Fashion Management

Authors: Susan Dillon

2nd Edition

1474271219, 978-1474271219

More Books

Students also viewed these General Management questions