Answered step by step
Verified Expert Solution
Question
1 Approved Answer
What is the expected duration for Activity B What is the Expected duration for this PERT schedule?' What is the critical path of this PERT
What is the expected duration for Activity B
What is the Expected duration for this PERT schedule?'
What is the critical path of this PERT schedule? |
What is the Early Start, Early Finish for Activity D?
What is the variance for Activity G?
What is the Late Start, Late Finish for Activity F? |
What is the probability that the project can be completed in 26 days? |
What is the probability that the project can be completed in 22 days? |
What is the total variance for the critical path? |
Use the following table of activities and their respective optimistic, most likely, and pessimistic activity durations the these questions. Be sure to carry two decimal places for activity durations.
Activity | Predecessor | optimistic | most likely | pessimistic |
A | - | 6 | 8 | 10 |
B | A | 1 | 2 | 3 |
C | - | 6 | 9 | 12 |
D | B | 2 | 5 | 11 |
E | C | 5 | 8 | 11 |
F | C | 2 | 4 | 8 |
G | D,E | 6 | 7 | 10 |
H | E,F | 4 | 6 | 8 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started