Question
What is the expected net present value E(NPV) of capacity plan (350, 450, 700)? * What is the expected net present value E(NPV) if we
What is the expected net present value E(NPV) of capacity plan (350, 450, 700)? *
What is the expected net present value E(NPV) if we were to invest in 350 Barracuda final assembly capacity, 450 Cheetah final assembly capacity, and 700 shared Test capacity? [all capacity numbers are in thousands]. Provide E(NPV) in millions with 2 digits after decimal point. So if your calculation shows that E(NPV) is $81,934,560, please insert 81.93 as your answer.
Question : Explain the pros and cons of the larger capacity plan (350, 450, 700) versus (300, 300, 600) *