What is the late start time for Activity E given the activity times and precedence requirements shown in the table? Activity Time Predecessor A 5
What is the late start time for Activity E given the activity times and precedence requirements shown in the table?
Activity | Time | Predecessor |
A | 5 | -- |
B | 7 | -- |
C | 8 | A |
D | 7 | A |
E | 4 | B |
F | 8 | C, D |
G | 9 | E, F |
H | 7 | G |