Question
1 Approved Answer
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? Normal Time (days) 6 Crash Time (days) 5 8
What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? Normal Time (days) 6 Crash Time (days) 5 8 6 4 3 5 3 8 5 Activity Design Wiring Chip install Software Testing The minimum cost of crashing the following project by 4 days is $ Normal Cost $900 300 500 900 1,000 (enter your response as a whole number). Crash Cost Immediate Predecessor(s) $1,000 400 600 1,200 1,600 A, B C