Question

1 Approved Answer

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Activity Normal Time (days)

What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?

Activity

Normal Time (days)

Crash Time(days)

Normal Cost

Total Cost with Crashing

Immediate Predecessor(s)

A

5

4

$800

$1,100

B

8

6

$200

$500

C

6

5

$600

$650

D

7

4

$750

$1,500

A

E

5

3

$1,200

$1,650

C

By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below.

(Enter

your responses as whole

numbers.)

Activity

Each Activity Should be Reduced BY

(days)

A

B

C

D

E

The total cost of crashing the project by 4 days is ?

(Enter

your response as a whole NUMBER)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions

Question

Cite the differences between type I and type II superconductors.

Answered: 1 week ago