What is the primary purpose of material requirements planning (MRP)? a. To provide manufacturing data relative to purchasing and shipping schedules of parts and components.
What is the primary purpose of material requirements planning (MRP)?
a. To provide manufacturing data relative to purchasing and shipping schedules of parts and components.
b. To improve the accuracy and detail of time schedules for parts and services.
c. To develop an assembly line estimate of lead time.
d. To calculate an EOQ relative to manufactured goods.