What is the primary reason for creating an improvement project charter? Question 6 options: 1) Identify a project leader and team members 2) Establish project
What is the primary reason for creating an improvement project charter? Question 6 options: 1) Identify a project leader and team members 2) Establish project scope and purpose 3) Clarify the project timeline and involved departments 4) Verify need for the project and its resources