Question

1 Approved Answer

What is the probability of finishing the project within a range of 3 weeks earlier than the expected completion time and 1 week later? Additionally,

What is the probability of finishing the project within a range of 3 weeks earlier than the expected completion time and 1 week later? Additionally, what is the probability of finishing the project 4 or more weeks beyond the expected completion time? Lastly, what due date would yield a 44% completion rate?

Standard deviation is 2.5 and expected completion time is 34 weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transportation A Global Supply Chain Perspective

Authors: Robert A. Novack, Brian Gibson, Yoshinori Suzuki, John J. Coyle

9th Edition

1337406643, 9781337406642

More Books

Students also viewed these General Management questions

Question

(1 + r)n +HnSn1d=c(n, Sn1d) and

Answered: 1 week ago