Question
1 Approved Answer
What should the project manager do to gain a stakeholder's approval if the stakeholder believes a project's deliverables were not achieved? A. Review the project
What should the project manager do to gain a stakeholder's approval if the stakeholder believes a project's deliverables were not achieved?
A. Review the project scope while analyzing the stakeholder's needs and expectations.
B. Perform a risk analysis after obtaining the stakeholder's new requirements.
C. Review the project charter thoroughly with this stakeholder on a conference call
D. Ensure that the stakeholder understands the quality management plan
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started