What term is used for the amount of time an activity can be delayed from its early start without delaying the planned project finish date?
What term is used for the amount of time an activity can be delayed from its early start without delaying the planned project finish date? a. free float b. backward pass c. total slack d. forward pass
Step by Step Solution
There are 3 Steps involved in it
Step: 1