When lot - for - lot is used for lot - sizing in MRP , order quantities for component parts are essentially determined directly from
When lotforlot is used for lotsizing in MRP order quantities for component parts are essentially determined directly from which one of the following?
gross requirements of that part
net requirements of that part
economic order quantity
net requirements of that part minus its projected onhand inventery