Question

1 Approved Answer

When performing Use Case Points ( UCP ) estimation, you estimate the number of Use Case Points at 2 0 0 UCP. The benchmark productivity

When performing Use Case Points (UCP) estimation, you estimate the number of Use Case Points at 200 UCP. The benchmark productivity for the software development lifecycle in that technology is 0.8UCP per person-day.
The estimated effort for that project including project management and other tasks should be:
Select one:
a. Greater than 250 person-days
b.160 person-days
c.250 person-days
d. Less than 250 person-days
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions

Question

12.28 The correct definition of resource leveling is:

Answered: 1 week ago