When work that is imminent is planned in detail while work that is way off in the future is planned only at a high level,
When work that is imminent is planned in detail while work that is way off in the future is planned only at a high level, the process is called
Select one:
i
Phase gates
ii
Rolling wave planning
iii.
Constant integration planning
iv
Continuous planning