Which of the following is a basic assumption of PERT? A . Only critical path activities in the network must be performed. B . There
Which of the following is a basic assumption of PERT?
A Only critical path activities in the network must be performed.
B There is only one complete route from the start of a project to the end of a project.
C Activity completion times are known with certainty.
D No activity in the network must be repeated.