Question
1 Approved Answer
Which of the following is NOT a limitation of PERT? Select one: a. Time estimates tend to be subjective and are subject tofudging by managers
Which of the following is NOT a limitation of PERT?
Select one:
a. Time estimates tend to be subjective and are subject tofudging by managers
b. Only one time estimate can be used for eachactivity.
c.
There is the inherent danger of placing too much emphasis on thecritical path.
d.
Precedence relationships must be specified and networkedtogether.
e.
Project activities have to be clearly defined, independent, andstable in their relationships.
Step by Step Solution
★★★★★
3.37 Rating (172 Votes )
There are 3 Steps involved in it
Step: 1
The detailed answer for the above question is provided below B Only one time estimate can be used fo...
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started