Which of the following is true about the duration estimates

Group of answer choices

The duration estimate helps to define the required resource for each project activity.

The activity durations are often estimated before estimating activity resources

The duration estimates may be progressively elaborated

Resources utilization could be helpful in estimating activity duration

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Of Art Galleries

Authors: Magnus Resch

3rd Edition

0714877751, 978-0714877754

More Books

Students also viewed these General Management questions

Question

What were some of the team norms at Casper?

Answered: 1 week ago

Question

What were some of the team roles at Casper?

Answered: 1 week ago