Question

1 Approved Answer

Which of the following statements regarding Scrum vs . Kanban is FALSE? Group of answer choices Scrum uses prescribed roles whereas Kanban uses existing roles

Which of the following statements regarding Scrum vs. Kanban is FALSE?
Group of answer choices
Scrum uses prescribed roles whereas Kanban uses existing roles
Scrum releases product as approved by the product owner whereas Kanban releases product at the team's discretion
Scrum's key metric is cycle time whereas Kanban's key metric is velocity
Scrum has timeboxed iterations whereas Kanban has continuous workflow

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions

Question

Describe the starategies used for general management

Answered: 1 week ago

Question

Discuss accounting cycle

Answered: 1 week ago