Which project(s) should a firm choose when the projects are independent? When they are mutually exclusive? Suppose both are within the capital budget and k
Which project(s) should a firm choose when the projects are independent? When they are mutually exclusive? Suppose both are within the capital budget and k is 15 percent for both projects.
Project A: CF0 = $1750; CF1 = $850; CF2 = $3850; CF3 = $1350 Project B: CF0 = $1750; CF1 = $850; CF2 = $850; CF3 = $4250
Both projects; project A
Neither project; neither project
Both projects; project B
Project B; project B