Which software project management metric measures the efficiency of resource utilization by comparing the actual work performed to the work planned? (5pts) Question 19 -
Which software project management metric measures the efficiency of resource utilization by comparing the actual work performed to the work planned? (5pts) Question 19 - Which software project management metric measures the efficiency of resource utilization by comparing the actual work performed to the work planned? Return on Investment (ROI) Net Present Value (NPV) Cost Performance Index (CPI) Earliest Start (ES)