Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project? a

Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project?
a.
definitive estimates
b.
parametric estimates
c.
bottom-up estimates
d.
analogous estimates

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

ISBN: 73403342, 978-0073403342

More Books

Students also viewed these General Management questions