Question

1 Approved Answer

Work station Minutes per item Capacity Order Taking 1 item per min 60 min / 1 item a min = 60 items per hour Pre-


Work station Minutes per item Capacity
Order Taking 1 item per min 60 min / 1 item a min = 60 items per hour
Pre- Treatment 60 min/ 56.8 items/ hour= 1.06 min/ item 90 items in 90 mins + 5 minute set up= 90/95 mins * 60 mins per hour = 56.8 items an hour
Dry cleaning

Tank Change (5 mins) + Run time (55 mins) = 60mins


90 items an hour/ 60min=1.5min/item

1.5 * 60 min = 90 items an hour
Pressing

There are 2 pressers which each press at 2.5 min.

2.5 mins per item with 2 pressers



60 min/2.5min per item= 24*2= 48 items an hour utilizing 2 pressers
Packing 0.5 mins per item 2 times a minute * 60mins = 120 items an hour
Pick up and Payment 1 min per item 1 Min per item * 60mins = 60 items per hour
  1. Customers have been complaining that stains are not removed properly. So the laundry reduces the batch size in pre-treatment to 75 items. Pre-treatment still takes 90 minutes plus 5 minutes for solvent tank change. Now what is the hourly capacity of pre-treatment? How does this impact the overall capacity of the process? 

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the new hourly capacity of the pretreatment process after reducing the batch size to 75 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Elements Of Chemical Reaction Engineering

Authors: H. Fogler

6th Edition

013548622X, 978-0135486221

More Books

Students also viewed these General Management questions

Question

=+a) Create a run chart for the baseballs weights.

Answered: 1 week ago