Work station Minutes per item Capacity Order Taking 1 item per min 60 min / 1 item a min = 60 items per hour Pre-
Work station | Minutes per item | Capacity |
Order Taking | 1 item per min | 60 min / 1 item a min = 60 items per hour |
Pre- Treatment | 60 min/ 56.8 items/ hour= 1.06 min/ item | 90 items in 90 mins + 5 minute set up= 90/95 mins * 60 mins per hour = 56.8 items an hour |
Dry cleaning | Tank Change (5 mins) + Run time (55 mins) = 60mins 90 items an hour/ 60min=1.5min/item | 1.5 * 60 min = 90 items an hour |
Pressing | There are 2 pressers which each press at 2.5 min. 2.5 mins per item with 2 pressers | 60 min/2.5min per item= 24*2= 48 items an hour utilizing 2 pressers |
Packing | 0.5 mins per item | 2 times a minute * 60mins = 120 items an hour |
Pick up and Payment | 1 min per item | 1 Min per item * 60mins = 60 items per hour |
- Customers have been complaining that stains are not removed properly. So the laundry reduces the batch size in pre-treatment to 75 items. Pre-treatment still takes 90 minutes plus 5 minutes for solvent tank change. Now what is the hourly capacity of pre-treatment? How does this impact the overall capacity of the process?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To calculate the new hourly capacity of the pretreatment process after reducing the batch size to 75 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started