Workstation Processing Time per worker (min/unit) # of workers 1 10 2 2 6 1 3 16 3 A. What is the bottleneck? B. What
Workstation Processing Time per worker (min/unit) # of workers 1 10 2 2 6 1 3 16 3
A. What is the bottleneck?
B. What is the process capacity?
C. What is the flow rate if demand is eight units per hour?
D. What is the utilization of each resource if demand is eight units per hour?