yellow are my answers. Are they correct? i need help finding the slack. thank you Roger Ginde is developing a program in supply chain management

yellow are my answers. Are they correct? i need help finding the slack. thank you image text in transcribed
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: b) The critical activities for the leadership training program development project are B. D. E-G c) The project length for the leadership training program development project = d) Slack time for each of the activities is

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Fundamentals

Authors: Robert N. Lussier

9th Edition

154438419X, 978-1544384191

More Books

Students also viewed these General Management questions

Question

How does natural writing improve ease of reading?

Answered: 1 week ago