You are asked to use the CAPM to calculate the cost of equity for a company for use in project valuation. Assume that the project

You are asked to use the CAPM to calculate the cost of equity for a company for use in project valuation. Assume that the project is roughly the same risk and duration as the company's existing projects, building construction projects making revenues from long-term lease contracts over several decades.

The annualized yield on 30-day treasury bills: 2.5%

The annualized yield on 30-year treasury bonds: 3%

The average market return from 1927-today: 11.6%

The forward looking market risk premium: 4%

Sample covariance of company stock with S&P500: 0.3

Sample variance of S&P500: 0.5

What is the cost of equity for the project according to the CAPM?

(Note that you don't necessarily need to use all of the data presented.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions