You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and

You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
\table[[Work Packages,W1,W2,W3,W4,W5,W6,W7,W8,W9,W10,W11],[A,9,1,5,,,,,,,,],[B,,,,6,7,5,,,,,],[C,,,,,,,9,9,6,9,7],[Total,9,1,5,6,7,5,9,9,6,9,7]]
At the end of Week 8, activity "C" is 50% complete. What is the Earned Value of this activity?
Use two decimal places in your calculations.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Natural Resource Management Reimagined

Authors: Robert G. Woodmansee

1st Edition

1108740138, 978-1108740135

More Books

Students also viewed these General Management questions